Author: rcarey
This week, the construction crew finished up work in the extensions and soon will be moving into the main body of the library to begin the next phase of work! But first, we will be closed next Friday, August 7, to allow the plumbers to finish up their work in the extension and install the…
This week, our construction crew moved inside and began setting up the HVAC, lighting, and painting the ceilings in the new additions. In the next few weeks, we will have a few closures (8/7 and 8/31) for our plumbers to make some progress and we will see the start of the new storytime room inside…
This week, the construction crew worked on the exterior ground, surrounding the new sidewalk with dirt. Inside the building, they began the prep work for the new flooring and laid the flooring in the expansions. As the work moves largely inside, we also had work on the HVAC system this week. See some photos from…
This week, construction crews worked diligently to get our gutters attached to the new additions just in time for the rain! We also had work happening inside the largest of the additions, where crews tiled the bathroom. See some photos below!
This week, sidewalks went in around the building, which will provide a new walking path that will allow for entering through the back and front doors of the building! See some photos of framing of the sidewalks and laying of the concrete below!
This week, work continued inside the new extensions to the library and our new cabinets and countertops arrived! We also saw the finishing of the exterior of these sections with features that match the existing building, making the new additions look like they’ve always been there! Take a look below at some of the pictures…
As the construction work turns internal, this week we’ve seen paint go on the walls for the new extensions! On the outside, the pergola above what will become the back entrance to the building is up and is a new feature we’re very excited about!
This week, we’ve had a lot going on at the library! After the completion of the new roof and laying the concrete for the patio, construction has moved largely indoors. We’ve seen plumbers and electricians in the building this week in addition to our regular construction crew. The crew also broke through the walls separating…
This week, the noise in the library is at a new record as the roof is replaced. First, the roof was added to the extensions and then the scraping of the old roof and placing of the new began. We are grateful for the hard work of the roofers getting this done safely and quickly…
As the weeks have gone by and more work has been accomplished on our new additions to the library, less and less is visible from the outside of the building, but the work continues inside! This week, plumbers, electricians, inspectors, and roofers all made their way into the new additions and things are moving along…
